Re: Planner-list partial resource usage?
- From: Massimiliano Franco <max-lists ycom ch>
- To: Planner-list gnome org
- Subject: Re: Planner-list partial resource usage?
- Date: Thu, 07 Feb 2008 13:51:51 +0000
Hi Kevin,
Create a new calendar for this person and change the working hour to,
say 08:00-12:00 for a 50%.
Planner should then automatically manage the load.
Max
Le mercredi 06 février 2008 à 12:35 -0700, Kevin Kempter a écrit :
> Hi List;
>
> Is there a way to setup a resource less than full time (say 50% utilization)
> and have the planner too automatically adjust the timelines , so for a 50%
> utilization then a 3 day task (3 work days) should span 6 calendar days?
>
>
>
> Thanks in advance
>
>
> /Kevn
>