Re: Planner-list partial resource usage?



Hi Kevin,

Create a new calendar for this person and change the working hour to,
say 08:00-12:00 for a 50%.

Planner should then automatically manage the load.

Max

Le mercredi 06 février 2008 à 12:35 -0700, Kevin Kempter a écrit :
> Hi List;
> 
> Is there a way to setup a resource less than full time (say 50% utilization) 
> and have the planner too automatically adjust the timelines , so for a 50% 
> utilization then a 3 day task (3 work days) should span 6 calendar days?
> 
> 
> 
> Thanks in advance
> 
> 
> /Kevn
>  