I've just installed v 0.14.2 on windows xp and I've put my project in.
I now want Planner to resolve my resource conflicts so that each
technician is only doing one task at a time. Can this be done?
Chris Johnson
Technical Team Manager
King Edward VII School
Sheffield
e:cjohnson kes sheffield sch uk