Re: [Planner] Duration and work time
- From: Kurt Maute <kurt maute us>
- To: Planner Project Manager <planner lists imendio com>
- Subject: Re: [Planner] Duration and work time
- Date: Tue, 30 May 2006 22:09:12 -0400
On Tue, 2006-05-30 at 21:54 +0200, Magnus Larsson wrote:
> Hi!
>
> I am trying to use planner for course-planning at a swedish university. I work
> with tasks and subtasks, and Iwould need to spread activitiy across rather
> long periods of time, like 5 days working time spread over 2 months calender
> time. When I try to set this for each subtask, it seems ok, but the main task
> shows the total calender time (duration) also as work time - where I would
> need the accumulated work time instead.
>
> Is there a way to correct this?
This is corrected in cvs, and will be included in v0.14, which I'm
planning on releasing this weekend.
> Also, I would like to customize the time scale, so I can have week numbers
> visible even when showing some 4 months in the window (right now only months
> are displayed in this case). Any ideas?
Time scale is not currently user configurable. Though I haven't done
any experimenting, it looks like we'd run out of room for week numbers
once you zoom out past the point where the top half of the header shows
Quarters, and the bottom half shows months.
--
Kurt Maute <kurt maute us>
[