On Thu, 2006-06-29 at 21:12 +0200, Magnus Larsson wrote:
> Hi!
>
> I would like to assign university teachers to tasks, and these resources
> are counted in hours, where 1700 is the year total but this can vary for
> individuals. I am very uncertain about how to do this with planner - if
> I simply read "units" as my "hours" something strange will happen in the
> resource overview, as I understand it. So is there a way do do this?
Not currently. The units is really a % allocation of the resource's
available time (per the pertinent calendar).
--