Re: [Planner] Scheduling tasks
- From: Kurt Maute <kurt maute us>
- To: Planner Project Manager <planner lists imendio com>
- Subject: Re: [Planner] Scheduling tasks
- Date: Mon, 21 Nov 2005 20:02:41 -0500
On Thu, 2005-11-10 at 10:20 +1100, Mark Jonathan Greenaway wrote:
> I have a project that I'm going to estimate the schedule of. There's one
> resource (me) assigned to all the tasks, but not all the tasks have
> strict dependencies on one another. I'd like to reschedule the tasks so
> that they don't all occur on the same day, because there's only one of
> me. How do I do this in planner? I can't manually move the tasks in the
> Gantt view, although I can extend their duration. Should I be using the
> Must Start No Earlier Than or Must Start On constraints in the Task view
> to do this?
Yes, other than dependencies, constraints are the only way to set the
start day for a task.
--
Kurt Maute <kurt maute us>
[