Swaroop Shere wrote:
Hello,
Hi,
I am a newbie trying to use the planner software for the first
time. My problem is how to generate the end date of any task? I read the
documentation and it said that the software generates end date from the
effort and resources, but it did not work. And I cannot even change the
end date manually, as the start date. I am using planner version 0.12.1.
What do you mean it doesn't work? The way it works is that the end date
is the start date + the duration. The duration is calculated from the
work effort and the assigned resources with their work calendars in
consideration.
You can also make tasks have a fixed duration instead where the work is
calculated from the duration.
/Richard
--
Imendio AB, http://www.imendio.com/
[