Re: [Planner] Task duration
- From: Tom Miller <trm xpedion com>
- To: Planner Project Manager <planner lists imendio com>
- Subject: Re: [Planner] Task duration
- Date: Thu, 20 Jan 2005 07:29:32 -0800
John,
I haven't used 0.12.1, but I know with its predecessor you
could work around this by using fractional days (or hours, if
you can switch it into that mode somehow). Hope this
helps at least a little.
Tom
On Thu, 2005-01-20 at 02:32, John Easy wrote:
> Hi
>
> I am looking to use Planner to manage my projects at work, but it would
> appear that I can only enter task durations in days. Is this true? I
> am running the latest version of Planner 0.12.1 under FC3 and although I
> can see in the help screens that the duration type should be a drop down
> menu it is not.
>
> Can anyone please enlighten me as to how to change this as some of my
> tasks need to be specified in minutes.
>
> Many thanks
>
> John
> _______________________________________________
> Planner mailing list
> Planner lists imendio com
> http://lists.imendio.com/mailman/listinfo/planner
[