Re: [Planner] gantt chart printing
- From: Bjorn Andersson <bjorn iki fi>
- To: Planner Project Manager <planner lists imendio com>
- Subject: Re: [Planner] gantt chart printing
- Date: Tue, 4 May 2004 21:40:42 +0300
> On Tue, 2004-05-04 at 17:29, Jasper de Jong wrote:
> > I have created a gantt chart that looks good on screen but when I print
> > it there are two elements missing that are both visible on-screen:
> > - the vertical 'today' timeline indicator
> > - the 'completeness' bar indicator inside a task bar
On Tue, May 04 2004, at 20:24:11 +0200, Christoph Begall wrote:
> Why would one want that in a printed Project plan? It is
> outdated the next day. Just curious...
Don't know what Jasper is going to use it for, but I can think of some
reasons:
- You want to show the plan at a meeting and you don't have a
laptop that you can use or feel more comfortable using a paper version
- You want to file a paper version of the project state e.g. once every
day, week or month so that you have a printed project history in a
printed project report
//Björn
--