Re: [Planner] Resource View



Great!

I am looking forward to it.

In the resource usage view, is it going to be similar to the old one with red where the resource is over commited still?

Would there be a way that we can do something like right click on the over-commited area, and in the tooltip it tells you which tasks the resource is overcommited on?

Undo would be great!

Also, are you aware of the bug when you double click on a task to modify its name and then go to a menu which results in a segmentation fault? I am using Debian/ and discovvered this bug yesterday - so I haven't got around to confirming the status with CVS.

Keep up the great work!

Regards,

Matthew

Xavier Ordoquy wrote:
On Wed, 2004-02-11 at 05:03, Matthew Tippett wrote:

Hello,


Hi


In earlier version of mrproject, there was the ability to look at resources and ensure that they were not over commited. I can't remember the view name, but it was there part way during between a couple of releases.


That was the timetable view.


Is there any chance of finding out if it can still be compiled in, or if there is any possibility that it will be back in the future.


Sure, I've been working on it to remove some bugs and it is now back in
planner cvs. It is now called resource usage.
The next release will also get undo/redo features which is complex to
code but will rock ;)

Regards,
Xavier Ordoquy.

_______________________________________________
Planner mailing list
Planner lists imendio com
http://lists.imendio.com/mailman/listinfo/planner




[Date Prev][Date Next]   [Thread Prev][Thread Next]   [Thread Index] [Date Index] [Author Index]