Re: [Planner] MrProject problem



Richard Hult wrote:
ons 2003-11-12 klockan 21.02 skrev Sergey Dolgopolov:

Hello!


Hi!


Problem:
In tasks time of the begin and end of a problem is not displayed.
I can select but then i select field is empty.


I'm not sure I understand what you mean. Could you perhaps take a
screenshot and put it somewhere? If you don't have www/ftp please make
sure the image is not too big if you post it to the list.

Regards,
Richard

Very strange!
I have LANG=ru_RU.KOI8-R and then I open project i not have date!
http://t205.narod.ru/image/planner_LANG_koi8r.jpg
Then i set LANG=C i see date.
http://t205.narod.ru/image/planner_LANG_C.jpg
May be you have idea how fix this problem?
Thanks for answer.
--
VIRG0-RIPE
VIRG0-UANIC




[Date Prev][Date Next]   [Thread Prev][Thread Next]   [Thread Index] [Date Index] [Author Index]