Re: [Planner Dev] Resource feedback



Sorry to come back to this old thread, but things don't work for me.
I've configured planner with "--enable-simple-priority-scheduling"
but what I get was:

Task 1: personn A: ********************
Task 2: personn A:           *****
                             ^^^^^
                                \ This is a problem :-)

100%: ****
50%:  ++++

Moreover, a great feature would be to set thickness of bar (in Gantt
view) proportional to the "charge" of people:

100% -> 10px (or whatever)
50%  -> 5px
...

So we may get things like (Task 2 is scheduled on fixed date)

Task 1: personn A: ==========------===== (priority N)
Task 2: personn A:           ------      (priority N)

or

Task 1: personn A: ==========      ===== (priority N+1)
Task 2: personn A:           ======      (priority N)


To finish, the last feature to make planner THE ultimate tool: the
ability to filter gantt view by resource (people). My aim is to print
schedule for each member of the team. (no, having a local webservice is
not what I prefer...)

Regard,

ps. where is the official repository? is it CVS or Arch?


Kurt Maute wrote:
> On Mon, 2006-04-17 at 19:02 +0200, Nicolas LAURENT wrote:
...
>> The "missing feature" is, for me, the ability to set "variable" the unit
>> in the association task-ressource. Actually, it could be great if
>> planner could do:
>>
>>
>> Task 1: personn A: **********+++++*****
>> Task 2: personn A:           +++++
>>
>> 100%: ****
>> 50%:  ++++
>>
>> Task 1 duration should be recomputed instead of setting person A
>> "over-loaded"...
...
>   ./autogen.sh  --enable-simple-priority-scheduling
> to enable the feature.