Hi Chuck,
> One thing I am trying to figure out with the project planner is, can
> one attach a fixed date to a task or milestone? In particular, if you
> are building a project which has external dependencies (i.e.,
> deliverables from another group), you may not know anything about the
> task other than the promised delivery date. I was looking at doing
> this through the use of a resource, but it wasn't obvious how this
> might be done...
I usually set up external dependencies as milestones, since like you said,
they have no duration or other info... just a due date.
If you right click on a task and bring up the Edit Task dialog box, you'll
find a check box to mark the task as a milestone. There's also a check box
for fixed duration in that dialog and other goodies as well.
-Kurt Maute
kurt maute us
[