Re: [Planner Dev] Uncertainty management / MonteCarlo simulation
- From: Mark Durrenberger <m durrenberger comcast net>
- To: Planner Project Manager - Development List <planner-dev lists imendio com>, Planner Project Manager - Development List <planner-dev lists imendio com>
- Subject: Re: [Planner Dev] Uncertainty management / MonteCarlo simulation
- Date: Thu, 01 Apr 2004 19:03:17 -0500
Comments in Line...
I think that you can just get the result of the simulation and take the
frequency with a given precision.
Not sure what you mean by this.
In the Gantt view what you are doing
actually is scheduling, so you should be able to chose the start and
finishing date to a given percentage of the probability to make it.
Of
course when the task is always away of the critical path you can choose
any number.
Actually one of the values of Monte Carlo is to see what the "most
probable" critical path is and for many projects there are multiple
critical or near critical paths. In these situations you'll have what is
called a "Merge effect" - think of it this way, I'm a parent of Triplets
(honest, age 11) On Saturday morning I say to the kids, hey, lets go
fishing. When do I actually back out of the garage? When the last kid gets
into the car not when the average kid gets into the car, not when the kid
plus one standard deviation gets into the car... Well projects often have
the same situation multiple critical or near critical paths...
So the only way to get a proper duration calculation is through a monte
carlo simulation...
I used python to do my Monte Carlo simulation program because it already
has a package for a lot of probability distributions (scipy).
great I assume we can use these in Planner.
I really think that it is not hard to do the simulation, but get harder
to integrate it visually with all the other things. Once you have your
uncertain durations, you should calculate your uncertain costs ;-)
I have lots of ideas on the visual aspect, even with limited access to MS
Project's user interface (you can't put graphics on the gantt chart for
example) I've been able to show the user duration means and standard
deviations etc.
Mark
[