[Evolution-hackers] multiple calendars per view



Hi

Here are all my thoughts on the implementation of having multiple
calendars per view.

First, JP and I have agreed on having the views use ECalendarModel, like
the task list. So, given the current situation in E*View, I've thought
about removing all the CalQuery usage in both EDayView/EWeekView, and
have their 'update_query' virtual method be called, from GnomeCalendar,
with the ECalendarModel to display.

This is quite easy to do, a bit tricky, since it involves some more
refactoring of the EDayView/EWeekView code, but shouldn't take long at
all.

The other part is to integrate multiple clients (that is, multiple
ECalendarModel's) in this stuff. We need to have each drawn event in the
views be associated with a CalClient (ie, a CalClient * member in
ECalViewEvent), so when calling the update_query virtual method, we need
to have a way to inform the views to which CalClient's each object
belongs to, so that it can associate them to the drawn events.

So, the simplest solution I can think of is to have the GnomeCalendar
manage the list of ECalendarModel's (one for each calendar) and pass
that to each view in the 'update_query' virtual method. Then, each view
just has to draw each event, identifying each one with the CalClient it
belongs to.

This way, all the query management would be done in only one place (the
GnomeCalendar) and views would just have to draw the events from the
calendar models they get in the update_query method.

cheers