[Ekiga-list] Ekiga, opal, pwlib is worth $ 17,945,674




Hi

I just run sloccount over Ekiga, opal, pwlib to se how much they are worth see breakdown below :)


Ekiga:
Totals grouped by language (dominant language first):
cpp:          24160 (67.21%)
ansic:        11661 (32.44%)
sh:             126 (0.35%)




Total Physical Source Lines of Code (SLOC)                = 35,947
Development Effort Estimate, Person-Years (Person-Months) = 8.60 (103.19)
 (Basic COCOMO model, Person-Months = 2.4 * (KSLOC**1.05))
Schedule Estimate, Years (Months)                         = 1.21 (14.56)
 (Basic COCOMO model, Months = 2.5 * (person-months**0.38))
Estimated Average Number of Developers (Effort/Schedule)  = 7.09
Total Estimated Cost to Develop                           = $ 1,161,682


-------------------------------------------------------------------------


OPAL:
Totals grouped by language (dominant language first):
cpp:         205891 (71.20%)
ansic:        83115 (28.74%)
sh:             170 (0.06%)
awk:             17 (0.01%)




Total Physical Source Lines of Code (SLOC)                = 289,193
Development Effort Estimate, Person-Years (Person-Months) = 76.79 (921.42)
 (Basic COCOMO model, Person-Months = 2.4 * (KSLOC**1.05))
Schedule Estimate, Years (Months)                         = 2.79 (33.45)
 (Basic COCOMO model, Months = 2.5 * (person-months**0.38))
Estimated Average Number of Developers (Effort/Schedule)  = 27.54
Total Estimated Cost to Develop                           = $ 10,372,628


-------------------------------------------------------------------------


Pwlib:
Totals grouped by language (dominant language first):
cpp:         144038 (88.57%)
ansic:        10936 (6.72%)
yacc:          3737 (2.30%)
sh:            2781 (1.71%)
lex:            969 (0.60%)
asm:            161 (0.10%)




Total Physical Source Lines of Code (SLOC)                = 162,622
Development Effort Estimate, Person-Years (Person-Months) = 41.95 (503.44)
 (Basic COCOMO model, Person-Months = 2.4 * (KSLOC**1.05))
Schedule Estimate, Years (Months)                         = 2.22 (26.59)
 (Basic COCOMO model, Months = 2.5 * (person-months**0.38))
Estimated Average Number of Developers (Effort/Schedule)  = 18.94
Total Estimated Cost to Develop                           = $ 5,667,348



Ekiga, opal, pwlib:
Total Estimated Cost to Develop                           = $ 17,945,674




Cheers Johnny