Planner-list Planner resources/tasks: How to handle people working part-time only?



Dear all,

I have started to use Planner just recently and I try to set up a project for which one person 50% of his time. I tried to accommodate that by setting the working hours in his calendar to 4 hours per day. Still, if I create a task with fixed duration, that takes 8 hours and should be completed within 2 days the person is assigned with 50% of his time instead of 100%. How can I get this consistent, i.e. have planner take into account that the work day length is not 8h for that resource? Or is there any other possibility to handle part-time workers?

Thanks a lot and best wishes
Sabine