I have a project schedule which is large enough to make the exported
planner HTML completely illegible. The Gantt chart is dozens of times
larger than the browser window, and there is no reasonable way to
navigate within the Gantt chart.
Given that, is there an easy way to customize planner to not include the
Gantt chart in the exported HTML, and instead include more complete
information in the "Tasks" list (like start & finish dates that include
the year)?
Thanks,
-Seb