Re: Planner-list Newbie Q - Resource Leveling



On Wed, 2007-04-25 at 11:26 -0400, Kurt Guenther wrote:
> Is there a way to do resource leveling?  That is, if I assign a resource
> (me) to all the tasks, can the tasks be automatically planned such that
> I'm at only 100% utilization.

I'm working on that functionality now.  It'll be part of the v0.15
release.

For now, you need to manually level the resources.


-- 