Hi, You have to "link" the 2 sub task to tell task2 goes after task1. File attached. Max Le jeudi 03 mars 2005 �2:57 +0100, Josep Mon�i Teixidor a �it : > Hi! > > I'm new to this list but I haven't seen this question answered in the > archives. > > I'm also new to project planning software so sorry if this is a lame > question. > > I have the following project: > 1. whole > 1.1 task1 10d > 1.2 task2 8d > > Imagine I assign task1 and task2 to resource resource1. Why does planner > schedule "1. whole" to be done in only 10d? I expected 18d here... > > Am I missing something? > > I attach a demo project which shows the problem I have. > > Thanks in advance, > > Josep > > > > _______________________________________________ > Planner mailing list > Planner lists imendio com > http://lists.imendio.com/mailman/listinfo/planner