hi
i open the Project properties dialog. In General tab, it has a "Start"
field, i try to type-in a day, then click "Close" button, no any changing.
I don't know it is a bug or i typed-in a wrong date format. In the old
version of mrproject, it will shows a calender and just click to choose,
it works. Why that change to type-in date by unknown format?
Could you please point me how to do for changing project starting date?
thanks
yan
[