Robi Karp wrote:
Hi,
Hi,
Is there a way to change the start date of a task?
Either by linking it or by setting a hard date. The latter can be done
in the task view, by clicking the start cell and choosing a constraint
type other than "as soon as possible".
Is there a way to have a Finish-to-Finish link?
No, not currently.
Regards,
Richard
--