Re: [Planner] problem with task lag propertie



ons 2004-02-11 klockan 18.52 skrev Emmanuel Saracco:
> hi,
> 
> lag propertie in predecessor section of a task do not act has it was
> expected.
> 
> planner documentation says that a value of 1 stand for "one day". but


It's actually hours in that field, but should be changed to accept the
same units as the rest of the interface (i.e. 2 = 2 days, 1d2h = 1 day 2
hours, etc).

There's a bug report on this:

http://bugzilla.gnome.org/show_bug.cgi?id=132357

/Richard

-- 
Richard Hult                    richard imendio com
Imendio                         http://www.imendio.com