Re: [Planner] assign resources
- From: Richard Hult <richard imendio com>
- To: Planner Project Manager <planner lists imendio com>
- Subject: Re: [Planner] assign resources
- Date: Thu, 29 Apr 2004 16:47:48 +0200
On tor, 2004-04-29 at 16:46 +0200, andrea pixel it wrote:
> when I try to assign resources to a task, the rectangle in the gantt view
> becomes shortest. more resources I add, more the rectangle becomes short.
> I think that the lenght of the rectangle depends on the number I assign to
> "unit". Is it true? What I have to do?
That's a correct assumption. If the task shouldn't depend on how many
resources you have, you can set it to a fixed duration task (in the edit
task dialog).
/Richard
--
Imendio HB, http://www.imendio.com/
[