Re: [Planner] Making tasks start later



tor 2004-02-26 klockan 21.20 skrev Waldemar Augustyn:

> >   
> Nicholas wants to find out when the task is supposed to start if the
> end time is determined.  I do not believe Planner can do it at this
> time.   In other words:  can you delay the END of the task?  Can you
> then deduce what the START of that task should be?  There are some
> hooks in the Task dialog, but I do not think they work.

Ah, I see. Yes, you are correct, that's not currently possible.

/Richard

-- 
Richard Hult                    richard imendio com
Imendio                         http://www.imendio.com